Project name . | Total cost ($) . | Cost/ft2 ($) . | Cost/Year ($) . |
---|---|---|---|
Northern Lights & Benson Resurfacing | 2 392 208 | 1.70 | 341 744 |
Tudor Road Pavement Rehabilitation | 5 928 633 | 3.08 | 846 948 |
Seward Highway MP 115–124 Resurfacing | 6 516 993 | 2.86 | 930 999 |
C Street (52 512) | 1 068 535 | 15.83 | 152 648 |
Minnesota Drive Resurfacing | 3 978 760 | 2.92 | 568 394 |
Glenn Highway | 10 274 557 | 2.08 | 1 467 794 |
Muldoon Road Resurfacing | 3 058 863 | 3.55 | 436 980 |
Sterling Highway Resurfacing | 1 645 616 | 1.27 | 235 088 |
Minnesota Drive Resurfacing | 3 679 828 | 4.17 | 525 690 |
Jewel Lake Road Resurfacing | 1 635 944 | 3.64 | 233 706 |
Glenn Highway MP 34–42 | 1 617 275 | 1.93 | 231 039 |
Sterling Highway Resurfacing | 2 779 942 | 3.11 | 397 135 |
Eagle River Loop Road Resurfacing | 2 063 762 | 2.46 | 294 823 |
Dimond Boulevard Resurfacing | 5 918 240 | 3.41 | 845 463 |
Glenn Highway Intersection Resurfacing | 2 425 790 | 3.37 | 346 541 |
Dimond Resurfacing | 3 856 123 | 2.85 | 550 875 |
Glenn Highway Resurfacing | 7 728 503 | 2.04 | 1 104 072 |
Anchorage Resurfacing, Boniface Parkway | 1 197 920 | 1.73 | 171 131 |
Anchorage Resurfacing, C Street | 759 774 | 2.26 | 108 539 |
Anchorage Resurfacing, Lake Otis Parkway | 853 825 | 2.07 | 121 975 |
Project name . | Total cost ($) . | Cost/ft2 ($) . | Cost/Year ($) . |
---|---|---|---|
Northern Lights & Benson Resurfacing | 2 392 208 | 1.70 | 341 744 |
Tudor Road Pavement Rehabilitation | 5 928 633 | 3.08 | 846 948 |
Seward Highway MP 115–124 Resurfacing | 6 516 993 | 2.86 | 930 999 |
C Street (52 512) | 1 068 535 | 15.83 | 152 648 |
Minnesota Drive Resurfacing | 3 978 760 | 2.92 | 568 394 |
Glenn Highway | 10 274 557 | 2.08 | 1 467 794 |
Muldoon Road Resurfacing | 3 058 863 | 3.55 | 436 980 |
Sterling Highway Resurfacing | 1 645 616 | 1.27 | 235 088 |
Minnesota Drive Resurfacing | 3 679 828 | 4.17 | 525 690 |
Jewel Lake Road Resurfacing | 1 635 944 | 3.64 | 233 706 |
Glenn Highway MP 34–42 | 1 617 275 | 1.93 | 231 039 |
Sterling Highway Resurfacing | 2 779 942 | 3.11 | 397 135 |
Eagle River Loop Road Resurfacing | 2 063 762 | 2.46 | 294 823 |
Dimond Boulevard Resurfacing | 5 918 240 | 3.41 | 845 463 |
Glenn Highway Intersection Resurfacing | 2 425 790 | 3.37 | 346 541 |
Dimond Resurfacing | 3 856 123 | 2.85 | 550 875 |
Glenn Highway Resurfacing | 7 728 503 | 2.04 | 1 104 072 |
Anchorage Resurfacing, Boniface Parkway | 1 197 920 | 1.73 | 171 131 |
Anchorage Resurfacing, C Street | 759 774 | 2.26 | 108 539 |
Anchorage Resurfacing, Lake Otis Parkway | 853 825 | 2.07 | 121 975 |
Project name . | Total cost ($) . | Cost/ft2 ($) . | Cost/Year ($) . |
---|---|---|---|
Northern Lights & Benson Resurfacing | 2 392 208 | 1.70 | 341 744 |
Tudor Road Pavement Rehabilitation | 5 928 633 | 3.08 | 846 948 |
Seward Highway MP 115–124 Resurfacing | 6 516 993 | 2.86 | 930 999 |
C Street (52 512) | 1 068 535 | 15.83 | 152 648 |
Minnesota Drive Resurfacing | 3 978 760 | 2.92 | 568 394 |
Glenn Highway | 10 274 557 | 2.08 | 1 467 794 |
Muldoon Road Resurfacing | 3 058 863 | 3.55 | 436 980 |
Sterling Highway Resurfacing | 1 645 616 | 1.27 | 235 088 |
Minnesota Drive Resurfacing | 3 679 828 | 4.17 | 525 690 |
Jewel Lake Road Resurfacing | 1 635 944 | 3.64 | 233 706 |
Glenn Highway MP 34–42 | 1 617 275 | 1.93 | 231 039 |
Sterling Highway Resurfacing | 2 779 942 | 3.11 | 397 135 |
Eagle River Loop Road Resurfacing | 2 063 762 | 2.46 | 294 823 |
Dimond Boulevard Resurfacing | 5 918 240 | 3.41 | 845 463 |
Glenn Highway Intersection Resurfacing | 2 425 790 | 3.37 | 346 541 |
Dimond Resurfacing | 3 856 123 | 2.85 | 550 875 |
Glenn Highway Resurfacing | 7 728 503 | 2.04 | 1 104 072 |
Anchorage Resurfacing, Boniface Parkway | 1 197 920 | 1.73 | 171 131 |
Anchorage Resurfacing, C Street | 759 774 | 2.26 | 108 539 |
Anchorage Resurfacing, Lake Otis Parkway | 853 825 | 2.07 | 121 975 |
Project name . | Total cost ($) . | Cost/ft2 ($) . | Cost/Year ($) . |
---|---|---|---|
Northern Lights & Benson Resurfacing | 2 392 208 | 1.70 | 341 744 |
Tudor Road Pavement Rehabilitation | 5 928 633 | 3.08 | 846 948 |
Seward Highway MP 115–124 Resurfacing | 6 516 993 | 2.86 | 930 999 |
C Street (52 512) | 1 068 535 | 15.83 | 152 648 |
Minnesota Drive Resurfacing | 3 978 760 | 2.92 | 568 394 |
Glenn Highway | 10 274 557 | 2.08 | 1 467 794 |
Muldoon Road Resurfacing | 3 058 863 | 3.55 | 436 980 |
Sterling Highway Resurfacing | 1 645 616 | 1.27 | 235 088 |
Minnesota Drive Resurfacing | 3 679 828 | 4.17 | 525 690 |
Jewel Lake Road Resurfacing | 1 635 944 | 3.64 | 233 706 |
Glenn Highway MP 34–42 | 1 617 275 | 1.93 | 231 039 |
Sterling Highway Resurfacing | 2 779 942 | 3.11 | 397 135 |
Eagle River Loop Road Resurfacing | 2 063 762 | 2.46 | 294 823 |
Dimond Boulevard Resurfacing | 5 918 240 | 3.41 | 845 463 |
Glenn Highway Intersection Resurfacing | 2 425 790 | 3.37 | 346 541 |
Dimond Resurfacing | 3 856 123 | 2.85 | 550 875 |
Glenn Highway Resurfacing | 7 728 503 | 2.04 | 1 104 072 |
Anchorage Resurfacing, Boniface Parkway | 1 197 920 | 1.73 | 171 131 |
Anchorage Resurfacing, C Street | 759 774 | 2.26 | 108 539 |
Anchorage Resurfacing, Lake Otis Parkway | 853 825 | 2.07 | 121 975 |